How long should it take to get a roof done?

How long should it take to get a roof done?
New charcoal architectural shingles on the steep main roof of an Oakland home after replacement
Reviewed for accuracy by Daniel Keshishyan, owner and C-39 licensed roofing contractor (CSLB #1090028).
Case Study · Oakland, CA · Steep Shingle Reroof

For this steep-roofed Oakland home, it was about eight weeks from the first phone call to a finished roof, and only the last few days of that were roof work. Most of the time went on the quote, the decision, paperwork and the city permit, which is normal for a full reroof.

New charcoal architectural shingles on the steep main roof of an Oakland home after replacement

How long should it take to get a roof done?

The roof work itself usually takes a few days on a typical house; the weeks go on everything around it. On this Oakland reroof the homeowner called on January 30, signed at the end of February, the permit cleared in mid-March, and our photos show the new deck and underlayment going on March 23 and the finished shingles on March 26. If a crew is on your roof for weeks with no weather or permit reason, ask why. A homeowner on r/Roofing asked exactly this.

The Home & the Challenge

Shingles coming off a very steep roof

The owners called because shingles were blowing off in the wind. The roof was about 26 years old, and the main roof on this home is unusually steep, a 14/12 pitch, which is steeper than 45 degrees. They asked for two quotes, one for a repair and one for a replacement. At that age, with shingles already letting go, replacement was the option that made sense.

Drone view of the 26-year-old shingle roof on an Oakland home before replacement
Before: the 26-year-old shingle roof from above.
Street view of the steep-gabled Oakland home before its roof replacement
Before: the steep front gable from the street.
The Solution

A full replacement with new plywood

The scope was a complete tear-off, new plywood decking across the roof, synthetic underlayment and new charcoal architectural shingles, under a City of Oakland permit. A roof this steep cannot be walked like an ordinary one, so the crew works from roof jacks, staging and fall protection, which is part of why steep roofs take longer and cost more. Our shingle roofing page covers the system in more detail.

The Process

Where the eight weeks went

January 30: first call. February 4: inspection and quote. February 27: contract signed. The next two and a half weeks went on paperwork and the city permit, and the job was cleared to start on March 16.

New plywood decking with underlayment rolls staged on the steep Oakland roof during replacement
During: new plywood on the steep main roof, with underlayment staged on the ridge.
Synthetic underlayment installed over new decking during the Oakland roof replacement
During: synthetic underlayment over the new deck.

On the roof, the old shingles came off, new plywood went down over the deck, and the synthetic underlayment went on, as in the photos dated March 23. The finished shingles are in the photos from March 26. The job then moved to final billing and the permit closeout, and it was completed in mid-April. For comparison, see our guide to how long a roof lasts in California.

The Results

Before vs. After

FeatureBeforeAfter
Shingles26 years old, blowing off in the windNew charcoal architectural shingles
Roof deckOriginal deckingNew plywood across the roof
UnderlaymentOriginal, at the end of its lifeNew synthetic underlayment
PitchVery steep main roof (14/12)Same pitch, roofed with fall protection and staging
PermitNoneCity of Oakland permit
Time on the calendarFirst call January 30Finished roof by late March
Finished steep shingle roof with new vent flashing beside the chimney in Oakland
New pipe flashings in the finished shingles on the steep slope of the Oakland reroof
After: new pipe flashings in the finished shingles.
Finished valley between two steep shingle roof planes on the Oakland home
After: the finished valley between two steep planes.
Why It Matters

What sets the pace for an Oakland reroof

In Oakland the permit, the weather and the roof itself set the schedule. Steep hillside and older homes like this one take more time on the roof than a low ranch house, and winter rain can push a start date by days. What should not happen is a roof left open for long stretches. Ask your roofer how many days the tear-off-to-shingles stage will take, and how they protect the house overnight. More of our work in the city is on our Oakland roofing page.

“They cleaned up the yard including using a blower on the driveway, front path, and lawns. Each day of work was the same.”— Christopher C., via Google
Questions

More questions about roof replacement timing

How many days does a roof replacement take?

For most single-family homes, two to five working days on the roof. Steep pitches, new decking, multiple layers to tear off, and rain all add time. On this Oakland home, our photos show deck and underlayment on March 23 and finished shingles on March 26.

Why does it take weeks to start after I sign?

Mostly permits, materials and scheduling. In Oakland, the permit has to be issued before tear-off can begin. On this job that took about two and a half weeks from signing.

Can a roof be replaced in the rain?

Not safely while it is open. Crews watch the forecast, tear off only what they can dry in the same day, and tarp anything left exposed. Rain usually delays a reroof by a day or two rather than stopping it.

Want a real timeline for your roof?

We will inspect it, tell you how many days the roof work will take, and walk you through the permit. See more finished work on our roofing projects page.